Commercial Glazing — Contractor Coordination Checklist

What GCs and property managers need to hand us for a clean, single-mobilization commercial glass install.

Before take-off

  • Architectural elevations and door schedule
  • Ceiling and flooring finish schedule (affects track and channel selection)
  • Acoustic performance target for partitions, if specified
  • Fire-rating requirements for any assembly
  • Site access, loading, hoist and after-hours restrictions

Documents we supply

  • Itemized quote with per-assembly pricing
  • Shop drawings for approval before fabrication
  • Certificate of insurance ($5M CGL) and WSIB clearance
  • Product data and safety-glazing certification
  • Warranty documentation at close-out

Scheduling reality

Glass is measured from the built condition, so partitions cannot be templated until track substrate, flooring and ceiling are complete. Building that two-to-three-week fabrication window into the schedule after finishes — rather than in parallel — is the single biggest driver of on-time glazing.

Single-mobilization strategy

Where the schedule is tight we can template in phases and install in one pass, provided each phase's finished conditions are locked. We will map that sequence with you at the pre-construction meeting.

Want this specified for your project?

Book a free on-site measurement and we'll apply everything above to your exact conditions.

Book a free estimate

More guides

Ready when you are

Let's make something
extraordinary in glass.

Free on-site measurement, itemized transparent pricing, and a written quote back within 24 hours — anywhere in the Greater Toronto Area.

24h
Quote turnaround
500+
Projects delivered
$5M
Liability insured
10yr
Craft experience